Marina Coast Water District - Regional Urban Water Augmentation Project

text
icons

Project Update 5/22/2018:

The Project is well underway with over 30,000 feet of pipe installed to date and the Blackhorse reservoir tank foundation installation underway.  

Pipe installation work along California Ave.  is ongoing southbound through night work.  The night work will continue through the Imjin intersection near the end of May.

A second pipeline crew is continuing daytime work on 5th Ave south into the CSUMB campus.  This crew will continue up 5th Ave, connecting at an existing pipeline at the intersection of Inter-Garrison around the Memorial Day holiday.

Paving restoration across the City of Marina and along General Jim Moore Blvd will be occuring sporatically over the next 4-6 weeks until completed. A 2-inch paving overlay will be installed through the streets of Marina in July.

Please check back here for continued updates and investigate  the links to left for maps and additional information on the project. 

 

Welcome to the Regional Urban Water Augmentation Project (RUWAP) website.  The project includes installation of a new recycled water pipeline and reservoir tank. Please look through the links to the left for project information including the Smart Map that will show current and upcoming construction progress along the pipe alignment. 

Other information available includes pipe alignment maps, copies of construction alert mailers and door hangers, as well as general project descriptions and timelines within the various jurisdictions.